October 2019 Updates

October 2019 Updates

October 2019 Updates WOODLANDS Underfloor heating installed and ready for screed WOODLANDS Screed completed WOODLANDS Aco drain installation completed WOODLANDS External areas hard cored and ready for slabs WOODLANDS Reclaimed paving laid to new entrance  THE FOLD...
September 2019 Updates

September 2019 Updates

September 2019 Updates WOODLANDS Plastered out and ready for floor insulation and screeding WOODLANDS New solid oak 6 part bifold doors installed WOODLANDS External works underway – very wet!!! WOODLANDS New solid oak main entrance door installed WOODLANDS Floor...
August 2019 Updates

August 2019 Updates

August 2019 Updates WOODLANDS  Roof slate work completed WOODLANDS First fix studwork completed WOODLANDS All areas dot and dab ready for finish plaster coat WOODLANDS Vaulted ceiling skim coat completed THE FOLD Stripping of existing roof coverings underway THE FOLD...
July 2019 Updates

July 2019 Updates

July 2019 Updates WOODLANDS Stonework and roof structure completed WOODLANDS Main structural opening to form new Kitchen completed WOODLANDS Roof lantern installed BRAME HALL FARM We are pleased to announce the award of a Contract to carry out major refurbishments and...
June 2019 Updates

June 2019 Updates

June 2019 Updates BECKWITHSHAW Interiors completed ready for floor coverings BECKWITHSHAW All externals completed and hanging baskets in place! WOODLANDS Demolition work underway WOODLANDS All set for ground floor concrete WOODLANDS – Ground floor concreting underway...
May 2019 Updates

May 2019 Updates

May 2019 Updates St Winifreds Road Rear Accoya screen installed St Winifreds Road Tiling works underway St Winifreds Road Underfloor heating being installed St Winifreds Road Screeding works underway Beckwithsaw Plastering works underway Beckwithsaw Underfloor heating...